Site Works Updates

VIBRATION UPDATE – 27th JULY

We are publishing today the Vibration Report from the site for last week. We will continue to post the data as we receive it during the demolition stage.


Temporary piling works 30th July

We want to make you all aware that we have to implement additional sheet piling as temporary works to enable us to excavate the main core area to the basement level. Due to the depth of the excavation these are being implemented to support the sides of the excavation whilst the works progress at both […] View Article


Works Update 24th July

Now the major piling work has been completed over the last few weeks and phase in the construction starts. These are the activities we are expecting over the next few weeks Completion of CFA piling anticipated next week. Sheet piling to core area start anticipated next week. Continue the construction of the concrete capping beam […] View Article


VIBRATION UPDATE – 19th JULY

We are publishing today the Vibration Report from the site for last week. We will continue to post the data as we receive it during the demolition stage.


VIBRATION UPDATE – 13th JULY

We are publishing today the Vibration Report from the site for last week. We will continue to post the data as we receive it during the demolition stage.


VIBRATION UPDATE – 6TH JULY

We are publishing today the Vibration Report from the site for last week. We will continue to post the data as we receive it during the demolition stage.


Works Update 1st July

We are pleased to update everyone on the completion of the piling works yesterday.  The piling with the vibration unit finished on the 24th June and the final hammer driving works completed yesterday, 30th June.  We are fully aware that this has been noisy work for our neighbours and we thank you for your forbearance […] View Article


VIBRATION UPDATE – 1ST JULY

We are publishing today the Vibration Report from the site for last week. We will continue to post the data as we receive it during the demolition stage.


Weekend Working 27th June

We are considering working this Saturday 27th June, depending on how well the back driving/drop hammering of sheet piling works go today.  We have agreed that no noisy works will take place before 10 am. We will post an update on Twitter as soon this is confirmed.  


VIBRATION UPDATE – 21ST JUNE

We are publishing today the Vibration Report from the site for last week. We will continue to post the data as we receive it during the demolition stage.