Site Works Updates

SATURDAY WORKING, 28th NOV

We would like to give advance notice that work will be taking place this weekend, 28th November. The contractors have all been reminded that no noisy works should commence before 9:00 am at weekends.


Saturday Working, 21st Nov

We would like to give advance notice that work will be taking place this weekend, 21st November.  The contractors have all been reminded that no noisy works should commence before 9:00 am at weekends.


Site Working Hours

We have received a complaint with regard to early working on site last weekend, 14th November.  We fully accept that no noisy, external or internal works should take place before 08:00 on weekdays and 09:00 on Saturdays as per the planning condition. We are assured by both contractors that they set out to abide by […] View Article


Tuesday 3rd November

Last night, Tuesday 3rd November the essential concrete works unfortunately overran for 30 minutes which meant the site was shut down at 7:00 pm. The pouring of concrete once started is difficult to stop and if pours have to be stopped mid-way then this work becomes abortive. To rectify, the concrete already poured would need […] View Article


Friday Works 2nd Oct

On Friday we are pouring 370 m3 of concrete for the basement of Halo and once we start we cannot stop! Depending on conditions and traffic we could be working a little later but we will keep any disturbance to a minimum.  


Tower crane install today

Today we start the work to install a tower crane at Halo. We hope this will not cause delay to traffic but please bear with us while safely do this work.


VIBRATION UPDATE – 27th JULY

We are publishing today the Vibration Report from the site for last week. We will continue to post the data as we receive it during the demolition stage.


Temporary piling works 30th July

We want to make you all aware that we have to implement additional sheet piling as temporary works to enable us to excavate the main core area to the basement level. Due to the depth of the excavation these are being implemented to support the sides of the excavation whilst the works progress at both […] View Article


Works Update 24th July

Now the major piling work has been completed over the last few weeks and phase in the construction starts. These are the activities we are expecting over the next few weeks Completion of CFA piling anticipated next week. Sheet piling to core area start anticipated next week. Continue the construction of the concrete capping beam […] View Article


VIBRATION UPDATE – 19th JULY

We are publishing today the Vibration Report from the site for last week. We will continue to post the data as we receive it during the demolition stage.