Site Works Updates

Late working on the 27th Oct

On Wednesday 27th October a transfer slab was being poured to Coopers Court when we ran into some failures in plant. This resulted in the pour taking considerably longer to complete than anticipated and us working into the night. Due to the nature of the pour we were unable to stop it half way through […] View Article


Halo basement works 4th Feb

Weather permitting we intend to cast the first Halo basement section tomorrow and it’s likely we may well need to work on past 18.00, we have anticipated to be complete around 19.00 and there will be a limited number of the team on site. We will do our best to keep the disruption levels as […] View Article


SATURDAY WORKING, 9TH JAN 2021

We would like to give advance notice that work will be taking place this weekend, 9th January 2021. The contractors have all been reminded that no noisy works should commence before 9:00 am at weekends.


SATURDAY WORKING, 28th NOV

We would like to give advance notice that work will be taking place this weekend, 28th November. The contractors have all been reminded that no noisy works should commence before 9:00 am at weekends.


Saturday Working, 21st Nov

We would like to give advance notice that work will be taking place this weekend, 21st November.  The contractors have all been reminded that no noisy works should commence before 9:00 am at weekends.


Site Working Hours

We have received a complaint with regard to early working on site last weekend, 14th November.  We fully accept that no noisy, external or internal works should take place before 08:00 on weekdays and 09:00 on Saturdays as per the planning condition. We are assured by both contractors that they set out to abide by […] View Article


Tuesday 3rd November

Last night, Tuesday 3rd November the essential concrete works unfortunately overran for 30 minutes which meant the site was shut down at 7:00 pm. The pouring of concrete once started is difficult to stop and if pours have to be stopped mid-way then this work becomes abortive. To rectify, the concrete already poured would need […] View Article


Friday Works 2nd Oct

On Friday we are pouring 370 m3 of concrete for the basement of Halo and once we start we cannot stop! Depending on conditions and traffic we could be working a little later but we will keep any disturbance to a minimum.  


Tower crane install today

Today we start the work to install a tower crane at Halo. We hope this will not cause delay to traffic but please bear with us while safely do this work.


VIBRATION UPDATE – 27th JULY

We are publishing today the Vibration Report from the site for last week. We will continue to post the data as we receive it during the demolition stage.