Site Works Updates

Construction Noise at Finzels Reach – An Explanation

Firstly, we are very sorry about the impact that the noise from the Halo construction site at Finzels Reach is having on some local residents and people working nearby. We recognise that this situation is particularly challenging during the lock down, when people in the city centre are spending more time at home and have […] View Article


Sound Monitoring Report to 31/05/2020

We are publishing today the most recent sound monitoring report to show sound levels during the current works.  We will be posting a full explanation of the current db levels on Friday. We are very aware that the noise levels from our piling operations have been particularly high in the last few days, we want […] View Article


Vibration Update – 2nd June

We are publishing today the Vibration Report from the site for last week. We will continue to post the data as we receive it during the demolition stage.


SITE WORKS 1ST JUNE

The following works are taking place this week: Pre piling auger rig in operation ongoing all week Sheet pile driving operations ongoing all week Sheet pile hammer operations Vibration and noise monitoring being carried out by Wrings and WD Deliveries of steel sheet piles every day Minor hoarding changes at pedestrian entrance to accommodate 1 […] View Article


Some very high noise levels – 27th May

Today work started on driving sheet piles with a piece of equipment called a Movax.  We have experienced some very high noise levels that appear to be above the levels we would expect. For this reason we are investigating this and naturally have stopped the operations at the moment. We will report back when we understand […] View Article


Timelapse Camera Feed

A time lapse camera has been installed which will be available throughout the Halo build. Check back to see the most recent image. 


Vibration Update – 26th May

We are publishing today the Vibration Report from the site for last week. We will continue to post the data as we receive it during the demolition stage.                        


Site Works 26th May

The following works are taking place this week: Pre piling auger rig in operation ongoing all week Sheet pile driving operations ongoing all week Sheet pile hammer operations from Wednesday onwards There are ongoing deliveries this week including Delivery of additional site welfare Tuesday Deliveries of steel sheet piles every day Please check back for […] View Article


Vibration update -18th May

We are publishing today the Vibration Report from the site.  The report shows a level on the 15th May above the VDV Limit.  This has been investigated by the monitoring contractor.  The spike has been identified on Friday, just after 7 pm, this large vibration event they believe could only have come from an impact […] View Article


Vibration Update – 15th May

We are pleased to be able to report that the noise and vibration levels of our demolition activities on site are significantly below the levels that they would then constitute an unacceptable nuisance. That is not to say that some of our neighbours will not be disturbed by the concrete pecker chipping away on the […] View Article